Olancho, Honduras

This is a project, to supply water for the community of Olancho, Honduras.  The project has been underway for X years, and the first phase of the project is near completion.  As of March 2015, the final concrete was poured on the roof to complete the 20,000 gallon water storage tank. This is a huge milestone as it signifies the end of the first phase of the water project.

We are now ready to set the wheels in motion for the second phase of the project. This phase entails installing the new well, the electrical pump, and pipelines and valves to connect to the 135 homes. We expect to accomplish these tasks during the second half of 2015.

Project Lead: Steve Tedesco,  This email address is being protected from spambots. You need JavaScript enabled to view it.